Connect Work Task Templates
Explanation
Use this activity to connect work task templates to a PM program.
You can connect work task templates
to a PM program. A single work task template can be connected to many PM programs.
Prerequisites
- Work Task templates must have been defined
in IFS/Preventive Maintenance.
- The work task templates defined should be active and
valid.
- Sites need to be specified in Valid For Sites tab on the PM
Program.
- Item Classes need to be specified in Applicable Objects
tab on the PM Program.
- The PM program should be in the Preliminary status.
System Effects
Work Task templates will be connected to the PM program.
Window
PM
Program
Related Window Descriptions
PM Program
Procedure
Connecting one work task template at a time:
- Open the
PM Program window, and
create a new PM program (F5) or query for an existing one (F3).
- Click the Valid For Sites tab and create a new record if
there are any more sites for which the PM program will be valid.
- Click the Applicable Objects tab and create
a new record if there are any more process classes and item classes for
which the PM program will be valid.
- Go to Work Task Templates tab and create a new record (F5).
- Enter the task template ID and revision in the
relevant fields. Use the List of Values. Repeat steps 4 and 5 as often as required.
- Save the information (F12).