Close Material Requisition Line

Explanation

This activity is used to close a material requisition line. If a material requisition line consisting of a non-inventory purchase part, gets canceled on the way, without reaching the purchase order receiving stage, the material requisition that the line belongs to will indicate a Partially Delivered status. You would need to close the incomplete requisition line so as to close the requisition as a whole.

Prerequisites

System Effects

Window

Material Requisition

Related Window Descriptions

Material Requisition

Procedure

  1. Open the Material Requisition window, and populate or query for the appropriate material requisition.
  2. Select the line that has been canceled as a purchase order in Planned status.
  3. Right-click and click Close.