Sequence Subtasks within a Task Card

Explanation

This activity is used to sequence the subtasks within a task card. The purpose of this activity is to support the process of sequencing the work for regular maintenance orders with connected maintenance events (i.e., non-ELS maintenance orders).

Prerequisites

To perform this activity, subtasks must have been defined for the task card.

System Effects

Window

Task Card 

Related Window Descriptions

Task Card
Task Card/Subtasks/Sequencing

Procedure

  1. Open the Task Card window and search for the desired task card.
  2. Click the Subtasks tab and then click the Sequencing sub tab.
  3. Create a new record (F5).
  4. In the Subtask ID field, enter the subtask. Use the List of Values to select a valid value.
  5. In the Preceding Subtask field, enter the predecessor. Use the List of Values to select a valid value.
  6. Save the information (F12).