Renumber Operations

Explanation

This activity is used to change the operation numbering step in a routing alternate or in a routing template.

Prerequisites

This activity requires several number of operations.

System Effects

As a result of this activity:

Window

Routing
Routing Template
Estimate

Related Window Descriptions

Routing/Routings
Routing Template
Estimate/Items/Product
Change Routing Operation Numbering

Procedure

To perform activity from Routing

  1. Open the Routing window.
  2. In the Routings tab, right click and select Renumber Operations.
  3. Give a value to Operation Numbering Step field if you are not going to use the default value set in the Site/Manufacturing/General tab.
  4. Click OK.

To perform activity from Routing Template

  1. Open the Routing Template window.
  2. In the header right click and select Renumber Operations.
  3. Give a value to Operation Numbering Step field if you are not going to use the default value set in the Site/Manufacturing/General tab.
  4. Click OK.

To perform activity from Estimate

  1. Open the Estimate window.
  2. In the Items/Product tab right click and select Renumber Operations.
  3. Give a value to Operation Numbering Step field if you are not going to use the default value set in the Site/Manufacturing/General tab.
  4. Click OK.