Define Labor Class
Explanation
This activity is used to define a labor class and the resources for a labor
class. Labor classes are used for capacity planning, representing groups of
labor, such as machine operators. Capacity calculation can be based on
individuals or groups. For large groups it is recommended to use group as base
for calculation and scheduling in order to enhance performance of the system.
This is especially important when scheduling with Constraint Based Scheduling
(CBS) server or Advanced Planning Board (APB), since all possible resource
combinations will be evaluated.
The labor class can also be used for planning of maintenance and project
activities in Resource Management. When CBS or APB is used for operation
scheduling, labor class will also act as a constraint for operations (similar to
work centers, tools and materials). CBS server or APB will load labor classes
and connected persons and use them as constraints when scheduling operations.
Prerequisites
To use capacity calculation based on individuals, persons need to be
registered. If the person is already registered as a resource, the associated
data is used. A person may be blocked or hidden as a person but still valid as a
resource. In that case it is still possible to connect the person to the labor
class.
If capacity calculation is based on group, no persons need to be registered.
System Effects
- A new labor class is created.
- Persons or group resource quantities are connected to the labor class.
- When a new labor class is created, cost sets 1, 2, 3, and 4 are automatically
created for it.
- The labor class ID will be available in the Lists of
Values to connect to routing operations.
- The labor class is also registered as a resource. The labor class will be connected to the resource structure that
is default for the company associated with the site.
- The person connected to a labor class is registered as a resource, and
connected to the resource group for the labor class.
Window
Manufacturing
Labor Class
Manufacturing
Labor Classes
Related Window Descriptions
Manufacturing Labor Class
Manufacturing Labor Class/Persons
Manufacturing Labor Class/Group
Manufacturing Labor Class/Cost
Manufacturing Labor Classes
Procedure
From Manufacturing Labor Class window
- Open the Manufacturing Labor Class and click New.
- In the Labor Class field, using no more than 10 alphanumeric characters, enter the name of the labor class you want to
create.
- Enter a description of the labor class in the Description field.
- In the Site field, select the site to which you want to connect the labor class.
Click List
of Values to select the site.
- Specify a calendar ID for the labor class. Click List of Values to select from available
calendars. The site calendar appears as the default.
- In the Sched Capacity field, specify whether the type of schedule capacity
used is finite or infinite.
- In the Capacity Calc Base field, specify whether the
capacity calculation will be based on indiviuals or group. If set as
Individuals, then the capacity of the group will be calculated
based on the parameters defined on the Person tab. If set as Group,
then the capacity of the group will be calculated based on the parameters
defined on the Group tab.
- If desired, select a cost center ID from the List of Values.
- Save the new labor class record (F12).
Using Capacity Calculation Based on Individuals
- Open the Manufacturing Labor Class/Person
tab. To add a
person to the labor class, click New.
- In the Person ID field, select a person from the list of values.
- If desired, enter values in the Notes and Utilization
fields.
- If you want to use the HR schedule as base for
capacity calculation, select the Use HR Schedule check box.
- If you do not want to use the HR schedule as base
for capacity calculation, specify a calendar ID for the person. Click List of Values
to
select from available calendars.
- In the Sched Capacity field, specify whether the type of schedule capacity
used for the person is finite or infinite.
- Save the record.
- In Start Date enter the date from which the resource
can be used.
- In End Date enter the last date on which the selected
resource can be used. This field can be left blank if there is no known end
date.
- In % in Group enter percentage of total work hours that
the employee is available for this resource group. The default value is 100.
The available percentage is used when calculating the capacity for the
resource group based on individual resources. The total available percentage
for an employee for all resource groups should not exceed 100.
- Repeat step 8-10 if resource availability differs over time.
Using Capacity Calculation Based on Group
- Open the Manufacturing Labor Class/Group
tab. To add a
new record, click New.
- If desired, enter the quantity to be used for capacity calculation in
the Resource Quantity for Calculation field. Calculated capacity will
equal Quantity x Available hours from calendar assigned to Company/Site.
- If desired, enter the utilization to be used to calculate utilization
capacity in the Group Utilization (%) field.
- In Valid From field enter the date from which the
capacity is valid for the resource group.
- If desired, enter the date until which the capacity is valid for the
resource group in the Valid to field.
From Manufacturing Labor Classes window
- Open the Manufacturing Labor Classes
window and click New.
- In the Labor Class field, using no more than 10 alphanumeric characters, enter the name of the labor class you want to
create.
- Enter a description of the labor class in the Description field.
- In the Site field, select the site to which you want to connect the labor class.
Click List
of Values to select the site.
- Specify a calendar ID for the labor class. Click List of Values to select from available
calendars. The site calendar appears as the default.
- If desired, select a cost center ID from the List of Values.
- In the Sched Capacity field, specify whether the type of schedule capacity
used is finite or infinite.
- In the Capacity Calc Base field, specify whether the
capacity calculation will be based on indiviuals or group. If set as
Individuals, then the capacity of the group will be calculated
based on the parameters defined on the Manufacturing Labor Class/Person
tab. If set as Group,
then the capacity of the group will be calculated based on the parameters
defined on the Manufacturing Labor Class/Group tab.
- Save the new labor class record (F12).