Set Maintenance Event to Work Done

Explanation

This activity is used to set a maintenance event with the distribution type Simplified Work Order to the Work Done status. This status is used to indicate that all task cards on the event have reached the Work Done status or a status higher to it.

Note: For events with distribution types Work Order and Execution Logic Structure, the status of the event will be set automatically to Work Done when the last task card on the event is set to work done.

Prerequisites

To perform this activity, the event must be in the Started status. To manually set the event to the Work Done status, the distribution type for the event must be Simplified Work Order.

System Effects

As a result of this activity, the event is set to the Work Done status.

Window

Maintenance Order

Related Window Descriptions

Maintenance Order
Maintenance Order/Maint. Order Str./Event Details
Maintenance Order/Included Events

Procedure

  1. Open the Maintenance Order window and query (F3) for the necessary maintenance order with the distribution type Simplified Work Order.
  2. Click the Maint. Order Str. tab.
  3. In the graphical object structure shown on the left, select the event you want. The Event Details tab will be updated with information on the event.
  4. Right-click, point to Status and then click Work Done.
  5. Observe that the status of the event is changed to Work Done.

Note: It is also possible set the status of an event to Work Done in the Maintenance Order/Included Events tab by using the above-mentioned Status feature.