This activity is used to set a maintenance event with the distribution type Simplified Work Order to the Work Done status. This status is used to indicate that all task cards on the event have reached the Work Done status or a status higher to it.
Note: For events with distribution types Work Order and Execution Logic Structure, the status of the event will be set automatically to Work Done when the last task card on the event is set to work done.
To perform this activity, the event must be in the Started status. To manually set the event to the Work Done status, the distribution type for the event must be Simplified Work Order.
As a result of this activity, the event is set to the Work Done status.
Maintenance
Order
Maintenance Order/Maint. Order Str./Event Details
Maintenance Order/Included Events
Note: It is also possible set the status of an event to Work Done in the Maintenance Order/Included Events tab by using the above-mentioned Status feature.