Review Planned Work
Explanation
This activity is used to view the defined work scope. This can be done on the
maintenance order or in the work order execution logic structure. The work load
can be reviewed to make sure that it will be possible to perform the work within
the allocated time and with the available resources.
Prerequisites
To perform this activity, a maintenance order must have been created and
released.
System Effects
As a result of this activity, the defined work scope is reviewed.
Window
Maintenance Order
Work
Order Structure
Work Order Planning Gantt
Related Window Descriptions
Maintenance Order
Maintenance Order/Maint. Order Str.
Maintenance Order/Included Tasks
Maintenance Order/Exec. Logic
Work Order Planning Gantt
Work Order Structure
Procedure
Use the following procedure to view a maintenance order:
- Open the Maintenance Order window and query (F3) for
the necessary
maintenance order.
- The tasks included on the maintenance order can be viewed in the
structure navigator displayed in the Maint. Order Str. tab or
on the Included Tasks tab.
- If the Execution Logic Structure distribution type is used, click
the Exec. Logic tab and then click the
Gantt sub
tab. To view the entire execution logic structure in the Gantt chart, select
the topmost node in the execution logic structure which is found to the
left of the tab.
Use the following procedure to view a work order execution logic structure:
- Open the Work Order
Structure
window and query (F3) for the necessary work order.
- View the structure of the work order in the work order structure displayed
to the left of the window or you click on the Work Order Planning Gantt
menu option to view the structure in a Gantt chart.