Refresh Resource Analysis Demand Snapshot

Explanation

Resource analysis can be performed on a snapshot of resource demand based on the parameters defined in the Resource Basic Data Window.

Prerequisites

Define Offset days in the Resource Basic Data window.

System Effects

Snapshot of resource demand for a defined time period is created. Timestamp field will indicate the time of snapshot being created.

Window

Refresh Resource Analysis Demand Snapshot

Related Window Descriptions

Refresh Resource Analysis Demand Snapshot

Procedure

1. Go to the Resource Analysis window.
2. Search for the resource/ resource structure.
3. Select the resource/resource structure in the navigator.
4. Use the Refresh Resource Analysis Demand Snapshot menu option.
5. Review the off-set values that previously defined in the Resource Basic Data.
6. Click OK or schedule the task.