Manually Reschedule the Work Order Structure

Explanation

This activity is used to manually reschedule the work orders in a work order structure.

Prerequisites

To perform this activity, the work order structure must exist.

System Effects

As a result of this activity, work orders and work order operations are rescheduled.

Window

Work Order Planning Gantt

Related Window Descriptions

Work Order Planning Gantt

Procedure

  1. Open the Work Order Planning Gantt window.
  2. Populate (F2) or query (F3) for the necessary work order number.
  3. Manually move the work tasks and work orders to the point in time where the work should be executed.
  4. Save the information (F12).