Use this activity to incorporate items in the work scope again, the work with the item that has been resumed. All items by default are created as Active and incorporated in the cost calculation. It is possible to set an inactivated item back to active as long as its top item isn’t Confirmed for any version.
You can manually set an inactivated item record to Active via right-click option, from either the tree structure or the item header. When executing this option then are all items in the branch, up- and down streams set to Active.
This activity requires that an estimate header that does not exist in status Confirmed, Completed, Closed or Cancelled. At least one item must exist as Inactive and it must be in status InProgress or Calculated.
As a result of this activity, an item record is again incorporated in the work scope and considered when performing a calculation.
Note: Activate of an item record can also be executed by right clicking from the item in the tree structure and selecting the same option as available from the item header.