Simulate Routing Cost
Explanation
This activity is used to simulate costs for routing alternates independent of the routing alternate status.
Note: You cannot perform a cost per routing calculation for cost set 1.
If part has a by-product, cost reductions related to the by-product will not be
taken into consideration when part routings cost is simulated or viewed.
Prerequisites
This activity has the following prerequisites:
- Cost sets must have been defined.
- A manufacturing or prototype routing must have been created.
System Effects
As a result of this activity:
- Costs will be calculated for the given routing alternate.
- Routing cost type cost records will be created for the part routing cost. Only the last simulation for a routing alternate will be saved.
Window
Part Routing Cost
Related Window Descriptions
Part Routing Cost
Procedure
- Open the Part Routing Cost window
and create a new record.
- In the Site field, click List and select the site for which you want to perform the cost
simulation.
- In the Part No field, click List and select the part for which the
simulation should be performed.
- In the Cost Set field, click List and select the cost set for which you want to perform the cost
simulation.
- In the Routing Rev/Alt field click List and select the routing revision/alternate
for which you want to perform the cost simulation.
- In the Lot Size field enter the lot size for which you want
to perform the cost simulation.
- Save the record.
- Click Calculate in order to calculate the cost for the given combination of structure and routing.