Set Contract Change Order to Submittal Approved
Explanation
Use this activity to set a contract change order (CCO)
to the Submittal Approved status. When the status has been set to
Submittal Approved, it indicates that documents, proposals for cost and
revenues etc. related to the change, are internally approved to be submitted to
the external parties e.g. a customer or a supplier.
Prerequisites
- A CCO should exist in the
Analyzed status.
- The External Approval Required check box is
selected in the Contract Change Basic Data/Change Type tab.
- Any approval lines and approval routing steps for
the current status, should be approved.
System Effects
- The CCO is set to the Submittal Approved status.
- A history record about the status change is created
and displayed in the Contract Change
Order/History tab.
Window
Contract Change Order
Related Window Descriptions
Contract Change Order
Procedure
- Open the Contract Change
Order
window and query for a CCO
in the Analyzed status.
- Right click on the header and click Status, then select the Approve before Submit
menu option.
- Click Yes to continue to set the CCO to Submittal Approved
status.