Set Contract Change Order to Analysis in Progress

Explanation

Use this activity to set an accepted contract change order to the Analysis in Progress status. When you set the status to Analysis in Progress, it means that the analysis of the change requirements should continue in the change process and be further investigated e.g. concerning the impact of the change.

Prerequisites

System Effects

Window

Contract Change Order

Related Window Descriptions

Contract Change Order

Procedure

  1. Open the Contract Change Order window and query for contract change orders in the Preliminary status.
  2. Select a contract change order that should be accepted. Right click and click Status, and then select the Start Analysis menu option.
  3. Click Yes to continue to set the contract change order to the Analysis in Progress status.
  4. Optionally, If the contract change order should be visible by a B2B supplier right click and click B2B Status, and then select Release menu option.