Recalculate Budget Values

Explanation

This activity is used to recalculate a budget version.

Prerequisites

Before recalculating the budget values, the following must have been completed:

System Effects

As a result of this activity, the budget values are recalculated.

Window

Budget Recalculation Rules

Related Window Descriptions

Budget Recalculation Rules

Procedure

Use the following procedure to recalculate the budget values:

  1. Open Budget Recalculation Rules and find the recalculation rule.
  2. Select the Apply Recalculation Rules operation, then specify Budget Year and Budget Version in the dialog box.
  3. Start the recalculation by confirming the information.